Kilsaran resurfaced 12km of carriageway on the M7 Kildare bypass pavement scheme for Jons Civil Engineering Limited. 

Completed using 15,000 tonnes of Hot Rolled Asphalt (HRA) and incorporating 15% RAP (recycled asphalt). The project used fine grade in all the HRA material apart from a 5000m area which received an incorporation of 35% RAP using the coarse grade, and a 5000m area with the standard HRA mix to act as a control. 

Overall, the use of the 15% RAP in the HRA material resulted in a 6.4% reduction in Carbon (4.9kg CO /Tonne) when compared with the Standard HRA. The use of 35% RAP in the HRA resulted in a 12% reduction in the Carbon (9.1kgCo2/Tonne) when compared with the Standard HRA. 

In all, this project achieved a 21% reduction in carbon emissions. 

Location: Leinster

Sector: Public

Products Used:

Roadsurfacing & Contracting:

Hot Rolled Asphalt (HRA)

Reclaimed Asphalt Pavement (RAP)

Main Contractor: Jons Civil Engineering Limited

Year of Completion: 2024